Main / Our projects / Expansion of Substation 220 kV Vanino for Branch of UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)
Commissioning of the new capacities on Substation 220 kV Vanino and Substation 220 kV Selikhino will provide conditions for the expansion of traffic capacity of Baikal-Amur Railway Road and enhance the power supply reliability for the consumers of Sovetskaya Gavan, Komsomolsk and Vanino districts of Khabarovsk Territory.
Engineering and packaged supply on a “turn-key” basis:
Substation equipment
High-voltage circuit-breakers 220 kV (Siemens AG)
Instrument current transformers
Reactor equipment
Disconnecting devices 220 kV
Cabling and wiring products
Modular constructions
Relay protection and automation systems, Automated process control systems, Communications systems, Electric power fiscal metering systems
The Customer: Elektrouralmontazh AO (JSC) under contract with UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)
Commencement of delivery: April, 2017
Completion of delivery: December, 2017
Amount of contract: RUB 500 million.