Main / Our projects / Energokomplekt ООО accomplished the delivery of materials for the construction of OHTL 110 kV in the process of connection of Substation 110 kV of Kamenskaya wind-power station and Sulinskaya WPP to the electric power networks.

  Supplies of:

Steel structures of towers and foundations

Precast concrete foundations

Cabling and wiring products

Reinforcement, fittings and accessories

Insulation

Bird control devices and wire marking

  The Customer:  Ural Power Engineering Construction Company АО (JSC) under contract with Wind Power Plant-2 of FRV Wind Farms ООО (Ltd.)

 Commencement of delivery: April, 2017

  Completion of delivery: December, 2017

  Amount of contract: RUB 500 million.