Główna / Aktualności / Energokomplekt carries out the equipment delivery for the city sewage treatment facilities construction c. Lytkarino
18.01.2021

Energokomplekt carries out the equipment delivery for the city sewage treatment facilities construction c. Lytkarino

Energokomplekt carries out the equipment delivery for the city sewage treatment facilities construction c. Lytkarino

The object is included into the government program „Engineering infrastructure and energy efficiency advancing” and is financed by federal funds, Moscow Region funds and Lytkarino city district funds.

The Customer of the project is “Housing and communal services and urban infrastructure development department of Lytkarino, Moscow Region”

Project duration 02.2021 – 08.2022

The scope of Energokomplekt delivery:

  • Flocculation tanks with protective grating Ø2200 mm.;
  • Water gutters for denitrifier drain feeding;
  • Primary settler float gutters LхBхH=1500х200х300 mm.;
  • Primary sludge bins;
  • Inlet chambers with a guide tube for external recirculation;
  • Water gutters;
  • Mixer units Ø2200 mm with the capacity of mixing tank 0,75 kW, voltage 380 V.;
  • Sludge densifiers D=3000 mm.;
  • Aerated blending tank 6х12х5,7 (h) m.;
  • Guide tubes for inner recirculation pump;
  • Guide tubes for discharge pump downdrop;
  • Flocculation tanks with protective grating Ø2200 mm.;
  • Water gutters for denitrifier drain feeding;
  • Drainage pumping station (complete) with the capacity of 75m³/h; Н=24m; N=11kW
  • Loading pits BxLхН=2300х2700х2000. Step 120mm.;
  • High-pressure centrifugal pumps Q=3,7m3/h; Н=4m; N=1,1 kW, n=1000 rpm Unilift KP 250 M 1;
  • Post-treatment bioreactor gutters (polymer filter);
  • Baffles of post-treatment bioreactor aerobiotic area (polymer filter);
  • Purolator filter gutters.