Main / Our projects / OHTL 220 kV Komsomolskaya-Selikhino for Branch of UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)

Commissioning of the new capacities on Substation 220 kV Vanino and Substation 220 kV Selikhino will provide conditions for the expansion of traffic capacity of Baikal-Amur Railway Road and enhance the power supply reliability for the consumers of Sovetskaya Gavan, Komsomolsk and Vanino districts of Khabarovsk Territory.

  Engineering and packaged supply of materials and equipment for HV-lines, on a “turn-key” basis:
Foundations
Towers
Wires and conductors
Line fittings and accessories

  The Customer: Ural Power Engineering Construction Company АО (JSC) under contract with UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)

  Commencement of delivery: April, 2017

  Completion of delivery: December, 2017

  Amount of contract: RUB 462 million.