Main / News and events / Energokomplekt has started supplying materials to the substation 220 kV "Naldinskaya" with approach lines 220 kV
05.03.2021

Energokomplekt has started supplying materials to the substation 220 kV "Naldinskaya" with approach lines 220 kV

Energokomplekt has started supplying materials to the substation 220 kV

In February, Energokomplekt OOO (Ltd.) delivered foundations to the construction site for the installation of lattice power lines.

The following goods are prepared for shipment:

— steel structures of high-voltage supports,

 — high-voltage wire brand AC 300/39;

— reinforced concrete foundations for the equipment of the substation;

— steel-frame housing of the substation control building and switchgear building;

— steel structures of internal and external fence system of the substation.

The construction of the substation 220 kV «Naldinskaya» with approach lines 220 kV is put into operation within the grid connection to the network 220 kV (FGS UES) for supply of electricity to consumers of the Inaglinsky mining and processing complex (KOLMAR Coal Mining Company).

The Inaglinsky Mining and Processing Complex is working on reserves of the Chulmakan coal deposit (central, eastern, northern and western bays) and Verkhne-Toluminsky coal deposit. The total production capacity of the new processing plant will be 12 million tons per year.