Main / News and events / Substation No. 505 Beskudnikovo 500 kV (the customer: Centre for Engineering & Construction Management AO (JSC)), was launched into operation
08.01.2020

Substation No. 505 Beskudnikovo 500 kV (the customer: Centre for Engineering & Construction Management AO (JSC)), was launched into operation

Substation No. 505 Beskudnikovo 500 kV (the customer: Centre for Engineering & Construction Management AO (JSC)), was launched into operation

On 31 of December, 2019, after a large-scale reconstruction, the key management centre for electrical supply of northern and northern-eastern districts of Moscow – Substation 500 kV Beskudnikovo – was put into operation.

Within the comprehensive program for technical upgrading and reconstruction of Substation 500 kV Beskudnikovo, Energokomplekt ООО carried out a complete delivery of the substation equipment for the amount exceeding 170 million rubles, as also performed some associated works, such as installation and adjustment supervision and training of the staff in the field of equipment operation. Energokomplekt will secure the follow-up technical maintenance and warranty service of the facility for its reliable operation.

Substation Beskudnikovo built in 1956 supplies energy to northern districts of Moscow and Moscow Region and falls under the 500 kV backbone network of Moscow power unit. The first stage of reconstruction was carried out in 2006-2009, thanks to which the substation capacity increased by more than 1.5 times. The next stage of reconstruction of the substation was associated with the transfer of overhead electricity transmission lines into underground tunnels for safety operation and transfer capacity improvement.

qr code