Substation 110 kV of Sulinskaya WPP and Substation 110kV of Kamenskaya WPP were put into operation

Wind Power Plants – In accordance with planned development of the wind industry in Russia, in December, 2019 the substation 110 kV of Sulinskaya wind-power plant and the substation 110 kV of Kamenskaya WPP were put into operation in Rostov Region. The connection of the substations to the national grid system of Russia was effected by the Ural Power Engineering Construction company AO (JSC) which built two high-voltage electricity transmission lines of total length equal to 14.5  kilometers.

Under the contractor agreement for the construction of high-voltage lines, Energokomplekt carried out the complete delivery of construction materials.

The two lines built were connected to the electric power networks of IDGS of South (Inter-Regional Distribution Grid Company of the Southern Region) PAO (JSC) providing the delivery of power of the wind power stations into the national grid system.

The total sum of the materials supplied exceeded 184  million rubles.